Wednesday, April 13, 2011
BACK DECK!!!
Monday, December 13, 2010
Live and Learn
Well now the house is done. It's beautiful and we love it. There are just a few loose ends that we are trying to get taken care of. Paint touch ups, some caulk repairs, etc. I'm pretty sure this project took a few years off my life - I now understand why people (usually) only do this once in their lives. I will never do this again, which is good, since we'll be living here forEVER. You live and learn - and if we had known then what we know now here are some things we would have done differently.
- I would have been how...do I say it - a hard-a$$, and not so nice right from the beginning. I was super nice to everyone, thinking that if they like me, they'll do a good job. I learned names and was sure to praise everything all the time. I think they did do a good job, but there came a point where I wasn't very comfortable "fussing" at them or pointing things out because I had set myself up as this nice mom with my kids in tow. I could have always loosened up but it's difficult to tighten up after you've been too nice.
- I would have inspected all the work much more thoroughly. It's uncomfortable after someone finishes a job to closely look over their work before you pay them - I like to trust that people have done a good job. Oh no. Not anymore. I wish I would have gone floor to ceiling, wall to wall, every single time. Because if I had, I wouldn't be finding these little imperfections that eat at me. Only toward the end do you become comfortable doing that kind of thing - just in time for the project to end.- I knew I didn't want white grout - I've lived that nightmare before. I went middle of the road. I would have gone even darker.
- We wouldn't have spent hundreds of dollars on a diverter valve for our master shower. We never use it - we both like both of the shower heads on all the time.
- I wouldn't have picked out berber carpet. It already has a ton of pulls and underneath it is concrete. Apparently the concrete is uneven and because the berber isn't very tall, in some spots there is space between the trim and carpet.
- I would have gotten MORE skylights. We installed 7 of the tube skylights. Seven. You would think that would be plenty, right? No, I wish we had at least 5 more. I LOVE them. On sunny days I don't even turn on a light in the house until 4:30. Also, they look like regular lights and people who are over don't even realize they're a skylight unless I tell them.
I'm sure I'll come up with more - and I'll just add them to the list. Overall we LOVE everything and are so grateful.
Wednesday, November 10, 2010
It happened!!
Tuesday, November 2, 2010
House Remodel - weeks 18 &19
Ok, I won't be Debbie Downer anymore about it. Especially if we get to move this weekend! It seems like it's never going to actually happen, so if it really does this weekend I'll have a renewed positive outlook on the entire project. Because let me just say, Dan has done an INCREDIBLE job! It's gorgeous and more beautiful than either Luke or I ever imagined it would be. Now we just want to LIVE THERE.
Monday, October 25, 2010
House Remodel - end of week 17
Yesterday I was there cleaning (the boys stayed overnight with my mom and Chuck) and I got the fireplace cleaned. I also got all of the outlet covers on - one doesn't realize how many outlet covers there are in a house until you're putting them all on! Then last night my mom and Chuck brought the boys up and the Thompson's came over and they helped me put in our closet system (hanging bars and a few (temporary) shelving units). Luke had to leave for Ohio yesterday afternoon so he wasn't there. We also had our first meal in the house (Sonny joined us too). Pizzas warmed up in our new stove! I'm kicking myself that I didn't take a picture. :( :( :( :(
Sunday, October 10, 2010
House Remodel - end of week 15
Last week the downstairs carpet was installed. The master carpet was delivered with a run down the middle (defective) so they had to send that back and order new. It should be in within a week or so. They removed the bamboo flooring upstairs and re-installed it (it was done poorly the first time). The appliances were delivered. The trim is almost finished. They've put in some finishing touches like the tops of the ledges in the upstairs hall above the living room and the 1/2 wall by the dining room. Also the outside is shaping up really well. The front gable posts have been put in place, the soffit is almost done and the siding on the front gable is almost finished!
We practically had to threaten Dan to give us an estimated time of completion (the inside) but he finally has. He said "a couple weeks." Yay! Two weeks! Little did I know that "a couple of weeks" is the big construction joke - as featured all over the place including SNL - as in "Sure lady. A couple of weeks. Mmmm hmmm."
Tuesday, September 28, 2010
House Remodel - weeks 13 & 14
On another brighter note, they have begun laying our tile! (no grout yet) This is the 1/2 bath upstairs. We will be using this same tile in the boys bathroom downstairs.

Here is the laundry room. I especially love this tile.

Sunday, September 19, 2010
House Remodel - Weeks 11 & 12
Our cabinets are in and our counter tops (quartz) and sink were installed. Most of our lighting fixtures are in. 
We are SO happy that we've gone with Dan Wesley as our "superintendent/builder." He has been nothing but wonderful. He is adding great touches to the house and has been honest, thorough and pleasant. One of the things we love about this house is not only that it is the house that Luke grew up in, but it's on the Payton land which includes farmland, woods and pasture. There is a beautiful old barn on the land that Luke absolutely loves. Dan took an old beam from that barn and cut it to fit on the end of the wall in our kitchen area. It looks incredible. He is also making our banister out of the old barn wood (which has "buckshot" (sp?) in it - when Luke's grandfather would shoot his shotgun some of the metal would lodge itself in the wood. You can actually see the tiny pieces in our banister if you look closely. What character!) It's gorgeous.
Tuesday, September 7, 2010
House Remodel - Week 10
Sunday, August 29, 2010
House Remodel - Weeks 8 & 9
Here is looking from the corner of the living room up into the kitchen and hall.
I am standing in what will be the kitchen looking down the hall and down into the living room.
Sunday, August 15, 2010
House Remodel - End of Weeks 6 and 7
The 2 downstairs bedrooms had small windows that were up high - on ground level. The times have changed and now you have to have 9 cubic feet outside a window and only be 4 feet off the floor to pass inspection as a "bedroom" for egress purposes. So we had to get larger windows for the 2 bedrooms downstairs and they dug window wells. One more thing we've encountered that we didn't plan on. (Which equals more time and more money)
The boys shower is in downstairs in the new bathroom.
One of the boys' bedroom downstairs. New window. We also ended up taking about 95% of the house down to the frame, which we didn't anticipate having to do.
We had to have the entire house re-wired. Something else we didn't anticipate. Things like the wiring and the support that we had to add, you can't tell those things until you really get in to the walls. Apparently they did things differently back in the days when this house was originally built since they found electrical wires duct taped together and nails thru wires. Again, these changes equal time and money, but we are ok with it since this will be our "forever" house and we definitely don't want any corners cut.
New stairs going up.
This is where the front door used to be, on the 2nd floor. They bumped out the wall to be even with the front of the house and added a window. This will be our "office nook".
View from upstairs looking down into the living room. (new garage is farther back)
Front door is in!! View from inside...
View from outside...
All of the new windows are in (except the large living room window) Also the new metal roof is finished. (it's hard to tell in this pic but the color is charcoal - dark gray) You can also see that little bubble on the roof. We put in 7 tube skylights that will provide some (green!) natural light for us.
Finally the outside of the house is almost finished. There is still quite a bit of brick and stone work to be done, and the back deck. But most major things are finished. I think now it will seem to go a lot faster.
Sunday, August 1, 2010
House Remodel - End of Week 5
I never put up pictures of the new living room stairs - here are the stairs going from the living room up. They did this a couple of weeks ago.